Rail Wheel Plant (RWP) Project, Bela
Chhapra - Setting up of Wheel Manufacturing Plant
SN
|
Project Parameter
|
Status/ Remarks
|
1
|
Pink Book Item
|
Original: 220/05-06/NER; Current: 19-20/RWP
|
2
|
Sanctioned Cost
|
Rs. 1639.50 crores (As per RE-4)
|
3
|
Location
|
Vill.–Bela (nearest Rly. Station Nayagaon 6 km away), Block – Dariyapur, District HQ – Chhapra, District – Saran, Bihar.
|
4
|
Cumulative Exp. up to Jan ’20
|
Rs. 1413.30 cr.
|
5
|
Target
|
August, 2020
|
6
|
Capacity
|
1 lakh BOXN wheel discs per annum.
|
7
|
Progress as on Jan '20
|
i) Physical Progress- 98%.
ii) Financial Progress- 86.2%.
|