Shakurbasti:Setting up of maintenance depots for train sets at shakurbasti
|
SN |
Project Parameter |
Status/Remarks |
|
01. |
Current Pink Book |
1148/NR/24-25 |
|
02. |
Last Sanctioned cost |
Rs. 213.36 Cr. |
|
03. |
Date of project sanction |
23.01.2020 |
|
04. |
Location |
Dhanbad Coaching Depot |
|
05. |
Target |
July 2024 |